Those stakeholders who have registered through this website will be informed of website updates, meetings and availability of (draft) documents.
Date (planned) |
Event/plan |
1 March 2025 |
Start of the ESPR Preparatory Study and Impact Assessment support study on tyres |
May 2025 |
Launch of the project's online platform and consultation questionnaire |
May 2025 (tentative date) |
Start of consultation of registered stakeholders for inputs on the development of the MEErP Task 1-4 reports (i.e. scope, market, users, technologies) |
September 2025 (tentative date) |
Interim draft Task 1 to 4 reports for stakeholder comments |
15 October 2025 |
First Stakeholder meeting on the MEErP Tasks 1 to 4 for registered stakeholders. |
February 2025 (tentative date) |
Interim draft of Task 5 to 7 reports for stakeholder comments |
March 2026 |
Second Stakeholder meeting on the MEErP Tasks 5 to 7 |
May 2026 |
Finalisation of the ESPR Preparatory Study Condition*: launch of the Impact Assessment support study |
July 2026 |
Condition*: drafting of Working documents for the Impact Assessment support study |
August 2027 |
Condition*: finalising of the Impact Assessment support study, contractual end of the project |
* work will proceed depending on the conclusion of the Commission services that an ecodesign regulation is the preferred approach